Foundations for Vulcanesti–Chisinau power line pillars 80 per cent complete

The construction site of the 400 kV Vulcanesti–Chisinau Independence Energy Line spans over 135 kilometers in both directions. To date, 224 pillars have been assembled, which is approximately 44 per cent of the total. At the same time, the foundation work is 80 per cent complete, with over 405 structures executed.

The Ministry of Energy today unveiled data to this effect, following a visit to the site by Minister Dorin Junghietu, in order to review the progress.

Preparations for stretching the conductor have recently started in Congaz, Comrat district. On the site, work is carried out simultaneously in the Hancesti district, on one side and in the Vulcanesti area, just one kilometer from the Vulcanesti Electric Station, where infrastructure modernization works are ongoing.

Also, works are carried out in the Autonomous Territorial Unit (UTA) Gagauzia and the districts of Leova, Cahul, Taraclia, Cimislia and Hancesti. Workers are operating in stages and in coordination, in order to observe the schedule established, Ministry of Energy said.

Meanwhile, at the Chisinau Electric Station, where the 400 kV line is to be connected, a modern system for monitoring the technical parameters of each autotransformer phase has already been delivered and is set to be installed in the near future. Moreover, the installation of 330 kV disconnectors is in the final phase.

The construction of the Vulcanesti-Chisinau Power Line started in April 2024 and is part of the Power System Development Project, financed by the World Bank Group. Its value is 61 million euros, of which about 27 million euros is for the Line's construction.

The 400 kV Overhead Power Line will be 157 kilometers long. Thus, over 500 pillars and 1,500 kilometers of conductors will form a strategic connection between the south and center, by crossing eight districts and 35 settlements. Depending on the energy system regime, the line can provide a flow transit of up to 630 MVA, which could meet 50 per cent of the energy consumption needs during peak periods.

The construction of the Vulcanesti-Chisinau power line is a strategically important project for Moldova's energy security. The new power line will allow the transport of electricity from Romania or other European markets to Chisinau, bypassing the Moldovan power plant located in the Transnistrian region.

 


 
Latest News
/ 11 May, 2026

Energy minister says developing energy storage capacities strategic priority for Moldova

/ 11 May, 2026

Works of reconstruction of passenger terminal of Eugen Doga International Airport – Chisinau: tender procedure relaunched

/ 08 May, 2026

CET-Nord joint stock company of Moldova announces tender for installation of electricity storage system at Balti-based combined heat and power plant

/ 08 May, 2026

Exports of Moldovan fruits to EU grow steadily: apples, sweet cherries record largest increases

/ 07 May, 2026

VIDEO // Discussions on sugar market situation held in Moldova; economic development minister says compromise reached

/ 07 May, 2026

National Bank of Moldova raises base rate for main monetary policy operations

/ 07 May, 2026

Prime Minister met with IMF expert team

/ 07 May, 2026

DOC // Single intermediary between producer and consumer

/ 07 May, 2026

DOC // Unified taxes and excise duties on both banks of Dniester

/ 06 May, 2026

First electrified railway segment of Moldova, part of connection with EU; Deputy PM says segment strategic step towards modern, cheaper, more efficient transport

/ 06 May, 2026

VIDEO // Moldova Presents exhibition to be staged in Brasov on June 27–28

/ 06 May, 2026

Energy Minister at SolarPower Europe Summit: Solar and storage systems are now instruments of sovereignty, resilience and secure access to energy

/ 06 May, 2026

Deputy Prime Minister about sugar market situation: We will hold discussions with all stakeholders

/ 06 May, 2026

IMF team of experts coming to Chișinău