Vulcănești–Chișinău Power Line: defective equipment at Chișinău substation repaired
Energy Minister Dorin Junghietu announced today that the defective equipment identified at the Chișinău Substation, which is part of the Vulcănești–Chișinău Power Line construction project, has been repaired in Spain and is scheduled to be shipped to the Republic of Moldova this week.
According to the official, after the equipment arrives in the country, the contractor will need approximately four to five more weeks to integrate it and carry out the necessary tests.
“I received information at the end of last week that the equipment sent to Spain for repairs has been completed and that this week it will be packed and sent by land to the Republic of Moldova. Once it arrives, the contractor will need approximately four to five weeks for integration. The installation does not take long, but all the integration tests for the substation require more effort,” Dorin Junghietu said.
The Energy Minister emphasized that the Vulcănești–Chișinău Power Line will eliminate the last structural dependency in the national electricity system. The minister noted that the line is complete and has been tested, but the works at the Chișinău Substation still need to be finalized.
“The line is complete and was tested under voltage, without load, on June 21–22. The Vulcănești Substation was also tested and accepted. We are now waiting for the contractors to finalize the works at the Chișinău Substation so that it can be commissioned,” Dorin Junghietu said.
Construction works on the Vulcănești–Chișinău overhead power line began in April 2024 and are part of the Electricity System Development Project, financed by the World Bank Group. The project is worth 61 million euros, of which approximately 27 million euros are allocated for the construction of the line.
The infrastructure of the line itself was completed as early as November last year, ahead of schedule, and was also energized up to the Chișinău Substation. However, the commercial commissioning of the entire project requires the completion of all works at the Chișinău Substation, including the testing and energization of the associated equipment.
The line is 157 kilometers long, crosses 35 localities in eight districts, and connects the 400 kV Vulcănești Substation with the 330 kV Chișinău Substation. It will be able to transmit up to 630 MVA of power, equivalent to more than 50% of the country’s electricity consumption during peak periods.
The construction of the Vulcănești–Chișinău Power Line is a strategically important project for the country’s energy security. The new power line will enable electricity to be transmitted from Romania or other European markets to Chișinău without passing through the Moldovan Power Plant, located in the Transnistrian region.
VIDEO // This year’s National Wine Day to bring together more than 110 producers in central Chișinău
DOC // Law on crypto-asset market published in Official Journal and enters into force
Natural gas prices on European exchange continue to rise; energy minister says international energy crises directly affect Moldova
Government approves ratification of agreement on construction of bridge over Prut River and first highway section in Moldova
Modernization works for district heating systems of Chisinau, Balti cities to be declared projects of national public utility
Companies from both banks of Dniester explore Romanian market to identify new opportunities for business expansion
VIDEO // Consumers to be able to compare natural gas and electricity suppliers’ offers in one place
Implementation of Growth Plan advances; Moldovan government prepares new package of projects to attract investments worth 2 billion euros
Grants worth over one million euros to develop Moldova’s innovation ecosystem with EU support
Convergence fund for Transnistrian region expected to finance infrastructure, education and public services
Application of national tax regime to goods from Transnistrian region enters new stage
Parliament votes in first reading on broad package of tax and customs amendments
Iași–Ungheni railway line to be rehabilitated and electrified
Moldovan Railways prepares new investments to strengthen railway connection to Giurgiulesti Port
VIDEO // Officials and international experts present opportunities for Moldova’s organic agriculture in Chisinau at Southeast European Conference
Modernization works for district heating systems in Chișinău and Bălți to be declared matter of national public utility
Obtaining permits and approvals for renewable energy production to be simplified
StratCom analyzes main vulnerabilities of regional information environment ahead of elections in Gagauzia
Parliament to examine legislative measures to strengthen NBM independence in line with European standards
PHOTO GALLERY // Journey through Northern Moldova through MOLDPRES lens
Prime Minister visits New York: bilateral meetings and address to plenary of UN General Assembly
Moldova and Kazakhstan strengthen cooperation
Moldovan and Romanian lawmakers to discuss cooperation in education
Moldovan PM says government must have necessary tools before crises materialize
Moldovan parliament approves establishment of state of emergency in energy, hydrological sectors for 60 days
Moldovan parliament declares nationwide state of emergency in energy, hydrological sectors for 60 days
Moldovan PM responds to opposition MPs on cutting fuel excise duty, value-added tax
Moldovan PM, European Commission official discuss accelerating growth plan projects
New director at Teleradio-Moldova Company: Ecaterina Cheptanaru wins competition
Moldovan parliament speaker explains need for state of emergency